An Update On The Gateway Tunnel Project

Gateway Development Corporation claim that they have found a $1.4 billion reduction in project cost estimates achieved through the advancement of design, engineering and technical efforts, as well as “encouraging private sector feedback and innovation” sounds great on paper. The devil is in the details. Have they shared the specifics of this $1.4 billion reduction in cost estimate with the Federal Transit Administration, Amtrak, New Jersey Transit and other potential funding agencies, along with transit advocates and elected officials? Have they performed any value engineering exercises to see if there are other construction options that could result in savings?

In 2015, the estimated cost for the Gateway Tunnel grew by $3.9 billion, from $20 billion to $23.9 billion. In 2017, the new cost estimate grew another $5.2 billion to $29.1 billion. Why five years later can they pull a rabbit out of the hat and come up with $1.4 billion in savings against an estimated $29 billion for the full build Gateway Tunnel? This new figure is based on reducing the estimated cost for both the new tunnel and rehabilitated old tunnel portions of the overall project which previously grew from $8.7 billion to $12.7 billion over time. Would whoever working for the GDC, that came up with the new project cost estimate. including $1.4 billion in promised savings, put up their pension, 401K or mortgage their home as collateral to guarantee that the design build process will deliver these savings? Design build is when you have the construction contractor advance final design beyond 30% in parallel with actual construction. One can only guess what the construction contractors winning bid will actually be. There is no way of knowing if it will come in higher than the new promised $11.3 billion for two new tunnels plus rehabilitation of the old tunnels. There are also contract change orders during construction. They are based on unforeseen site conditions or last minute changes in scope. Amtrak, Port Authority and GDC must share the details to justify these promised savings. Without this information, riders, taxpayers, transportation advocates and elected officials will remain skeptical.

Historically as any major capital project advances through design and engineering, estimated project costs rise. Responses to any construction procurement can easily come in above the project engineers estimate. Any final project cost upon completion could increase based upon responses to bids, along with change orders during construction. It would be interesting to see the detailed project budget for Gateway by line item including how much money has been programmed for contingency. These dollars which would pay for contract change orders during construction.

As a result of COVID-19, the world we live in has changed. Commuting patterns will be different. More people will telecommute on permanent basis. The concept of urban central business districts will continue to evolve. More people will be shopping on line. More Wall Street financial institutions and major corporations based in Manhattan may continue to move additional employees to suburban back offices.

Any ridership modeling for the Gateway Tunnel dealing with anticipated increase in ridership over the coming decades must be reevaluated.

The number one priority for the MTA, LIRR and others will be safety and security as a result of COVID-19. New maintenance activities, which may become permanent, will go on for the foreseeable future. New capital improvements to buses, trains, commuter rail, ferries, stations and terminals to deal with COVID-19 may take several years before fully implemented. Funding agencies such as the FTA will make the review, approval and oversight of billions in COVID-19 projects and programs the number one priority.

The Gateway Tunnel project is reminiscent of the ongoing MTA LIRR Eastside Access to Grand Central Terminal project. In 2001, the initial estimated cost was $3.5 billion with a completion date of 2011. In 2019, eighteen years later (based upon the 2016 MTA FTA amended Full Funding Grant Agreement) currently at $11.2 billion, it could grow to $12 billion with completion in 2022. Will Gateway do the same and become our New York version of the infamous Boston “Big Dig” end up costing $40, $50 or even $60 billion and completed by 2040?

Larry Penner is a transportation advocate, historian and writer who previously worked 31 years for the United States Department of Transportation Federal Transit Administration Region 2 New York Office. This included the development, review, approval and oversight for billions in capital projects and programs for the MTA, NYC Transit, Long Island Rail Road, Metro North Rail Road MTA Bus, NYC DOT, New Jersey Transit along with 30 other transit agencies in NY & NJ.

Larry Penner
Larry Penner is a transportation historian, advocate and writer who previously worked 31 years for the Federal Transit Administration Region 2 NY Office. This included the development, review, approval and oversight for grants supporting billions in capital projects and programs on behalf of the MTA, LIRR, Metro North, NYC Transit, NYC DOT, New Jersey Transit, NICE bus and 30 other NY and NJ transit operators. The opinions expressed are not necessarily those of the publisher or Anton Media Group.

Leave a Reply

Discover

Sponsor

Latest

Calendar of Events, June 16-27

Here is a sampling of the happenings in the Long Island Weekly coverage area. Wednesday, June 16 Bird Walk Hosted by the North Shore Audubon Society at...

County To Offer Summer Entertainment Series

Nassau County Executive Laura Curran announced a full slate of free events this summer, starting with a lineup of rockin’ summer concerts at the...

Police Trailblazer Is Memorialized

Headquarters named after Commissioner William Willett William J. Willett Jr. (1931-2003) was the Jackie Robinson of the Nassau County Police Department. No, he wasn’t the...

The Black Crowes Take Flight Again

When Chris and Rich Robinson made the November 2019 announcement that the Black Crowes were reuniting, it represented a reconciliation between the siblings after...

Rich Robinson’s Black Crowes Cover Faves

When it comes to bands that have a deep appreciation and reverence for rock and roll history, The Black Crowes have always been unabashed...

Get Updates Via Email

Enter your email to be updated with all the latest news and special announcements.

x